Council approves change order and extra construction-administration services for city projects

Greenville City Council · May 1, 2026

Summary

Council approved change order No. 20 with APGuild ($43,989) to move substantial completion to June 15 and to cover superintendent time and omitted AV cabinet; the council also authorized additional construction-administration services and short extensions to consultant scopes for project closeout and pool completion checks.

Council approved change order No. 20 with APGuild in the amount of $43,989 to extend the project's substantial completion date from May 17 to June 15, pay for superintendent time during the extension, and add an AV cabinet and some electrical design work omitted from the original specs. Project staff said the change order keeps the overall project within budget and primarily pays for labor time during the extended period.

Council also approved a services-proposal amendment to extend construction-administration work with the project's architecture and engineering consultants (weekly pool checks and RFI review) to cover the additional construction window. "The majority of this change order is going to be moving the substantial completion date, from 05/17 to 06/15," project staff said. Both items were approved unanimously.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source