Council approves $227,000 low bid to recoat East Tank interior; work timing weather‑dependent
Summary
The council authorized awarding the East Tank interior recoating contract to Cunningham Sandblasting & Panning for $227,000 per JEO Consulting recommendation; the utilities superintendent said work timing depends on weather and the contractor's schedule.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Utilities Superintendent Tory Zuver recommended awarding the East Tank interior recoating project to Cunningham Sandblasting & Panning, the low responsive bidder at $227,000, noting JEO Consulting Group’s recommendation letter and vetting. "Low bid was Cunningham Sandblasting and Panning Company. They came in at 227,000," Zuver said.
Council asked about the contractor location and schedule; staff said the company is based in Joplin, Missouri, and that the work is weather permitting and likely to be scheduled as a spring project if interior access or conditions prevent fall work. Members said they were comfortable with JEO’s vetting and that the award follows the procurement recommendation.