MAPS awards Marquette Senior High POD AC replacement to Prime Specialty Contracting
Summary
The board voted 5-0 to award the Marquette Senior High School POD AC replacement to Prime Specialty Contracting. Prime's base bid was $324,899; with recommended alternates (Trane factory start-up and conversion to DDC controls) the total is $358,376. IDI recommended a 7% contingency (~$25,000).
Get email alerts on the School Facilities topic
No spam. Unsubscribe anytime.
The Marquette Area Public Schools Board of Education on June 2 approved awarding the Marquette Senior High School POD AC Replacement Project to Prime Specialty Contracting following a recommendation from the district's architect/engineer. Superintendent Zack Sedgwick presented the project information and the board voted 5-0 to award the contract (mover: Jennifer Ray; seconder: Jennifer Klipp).
Integrated Designs Inc. (IDI) documented that Prime's total base bid was Three Hundred Twenty-Four Thousand, Eight Hundred and Ninety-Nine Dollars ($324,899.00). IDI recommended accepting voluntary alternates for a Trane factory start-up and converting pneumatic controls to DDC for the main air-handling unit, which raise the contract total to $358,376.00. IDI advised the district carry a contingency of approximately 7% (about $25,000) to cover unexpected items or scope adjustments.
The board recorded the award motion and carried it without recorded opposition. Implementation steps noted in the recommendation include issuing a notice of award once the district provides direction to IDI.