Pilot Hill Trailhead project accepted; $103,436 final payment advertised

Board of County Commissioners of Albany County, Wyoming · August 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board accepted final completion of the Pilot Hill Trailhead improvement project and directed advertisement for the contractor Archon's final payment of $103,436 on a total contract cost of $2,068,670.

County staff presented the Pilot Hill Trailhead improvement project for final acceptance and requested that the board direct advertisement for the contractor’s final payment of $103,436. Project representative Sarah (S10) said a few final items remain and that the University of Wyoming is completing some work under the contract, but staff recommended final acceptance; the board approved final acceptance and to advertise the final payment.

The staff report listed the original contract cost as $2,068,670.00 and commissioners congratulated project staff for completing the bulk of the work. The motion approved acceptance of the project and authorization to advertise the final payment to Archon in the amount specified in the staff packet.