Update given on Mason High cooling project; RFP timeline set to go out 11/17
Summary
Presenter Christman updated the committee on the Mason High additional cooling project and said the final bid packet will be issued as an RFP after Board authorization; draft schedule shows bids released 11/17 and opened 12/17.
Get email alerts on the Hvac Project topic
No spam. Unsubscribe anytime.
Christman updated the Finance & Property Committee on the additional cooling project at Mason High School and said the final bid packet will be issued as a formal RFP once the full Board authorizes the project. Christman noted the draft plans "include going out to bid on 11/17 with bid opening on 12/17."
Committee members asked about sequencing and contractor oversight; staff said they will return with a formal RFP and timeline for Board authorization. The committee recorded the update and will consider the RFP after the full Board takes the authorization step.