Council approves replacement of collapsing 8-inch sewer main on Park Street

Greenville City Council · April 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

No Dig Tech LLC will replace about 1,100 linear feet of 8-inch sewer main and rehab four manholes on Park Street between 2nd and 4th at an approximate bid of $300,007; council approved the resolution.

City Public Works staff told the council that an 8-inch sewer main on Park Street between 2nd and 4th is showing signs of collapse and recommended a replacement and manhole rehabilitation contract.

"The exact same thing... the 8 inch main is starting to collapse. And so they're gonna replace 1,100 linear feet," Public Works staff said, citing a bid around $300,007. Councilors asked whether these projects reflect isolated incidents or broader aging infrastructure; staff replied they respond to repeated calls and CCTV inspections and that these locations were prioritized after service complaints.

Council approved the resolution by motion. Staff said the work will proceed to address recurring backups and reduce emergency responses in the corridor.