Buildings & Grounds update: cold storage completion rescheduled; district remains within budget, official says
Summary
Director of Buildings & Grounds Mike Yale reported outside cold storage for the PAC and maintenance buildings is now scheduled to be completed "by the first of the year," delayed from an original October target, and the district currently lacks occupancy for those spaces. Deputy Superintendent Anderson said meetings with Miller Davis show several projects realized savings and funds remain available.
Get email alerts on the Buildings And Grounds topic
No spam. Unsubscribe anytime.
Mike Yale, director of buildings and grounds, told the committee that cold storage for the PAC and maintenance areas is now scheduled for completion by the first of the year; the project had missed an original October target and the district currently does not have occupancy for those buildings. The minutes record the revised completion timing but do not provide a new target date beyond "by the first of the year."
Deputy Superintendent Lisa Anderson said she met with Lance from Miller Davis, who oversees budgeting and finances, and that several projects realized savings so the district remains within budget with funds still available. The committee discussed potential wish-list items to allocate remaining dollars; no specific amounts or approvals were recorded at this meeting.