Board hears bid recommendations for paving and partial high‑school roof totaling $970,999
Summary
Consultant Collin Frink and Plante Moran/Realpoint recommended awarding the middle‑school/administration paving project to Al's Paving ($482,509 plus $75,000 contingency = $557,509) and a partial high‑school roof replacement to Lutz Roofing ($375,900 plus $37,590 contingency = $413,490). Both recommendations will go to the Feb. 25 regular meeting for approval.
Get email alerts on the Bond Projects topic
No spam. Unsubscribe anytime.
Collin Frink presented bid proposals and the recommendation of Plante Moran/Realpoint for two bond‑funded projects: the middle school/administration building paving project and a partial roof replacement at the high school. The paving bid recommendation to Al's Paving included hard construction costs of $482,509 and a construction contingency of $75,000, for a total award recommendation of $557,509. The roofing recommendation to Lutz Roofing listed hard construction costs of $375,900 and a contingency of $37,590, for a total recommendation of $413,490.
Mr. Frink also presented an updated bond budget sheet and answered questions from board members about project timing and contingencies. The board was informed that both recommendations will be presented for a formal vote at the board's Feb. 25 regular meeting. No motion or vote on these bids was recorded at the Feb. 11 work session.