Council accepts maintenance securities and approves Shades Phase 2 pay requests totaling nearly $495,000

Town of Cedar Lake Town Council (with Redevelopment Commission) · August 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved acceptance of multiple maintenance letters/cash bonds (Beacon Point $177,362.83; Birchwood Farms extension $395,168.95 contingent; Wicker Enterprises cash bond $2,133.00; Cedar Lake Storage listed amount) and approved Shades Phase 2 pay requests #3 ($268,468.26) and #4 ($226,965.02); motions carried 6–0.

Council reviewed and approved several development-related financial securities and contractor pay requests at the Aug. 4 meeting.

On BZA and plan items the council accepted a maintenance letter of credit for Beacon Point Units 6 & 7 for $177,362.83 (to expire 07/27/2029). It accepted a maintenance-letter extension for Birchwood Farms units 1–3 and 5 with the dollar amount in the packet (first-source / bank amount listed at $395,168.95) contingent on engineering and Plan Commission sign-off. Council also accepted a Wicker Enterprises cash bond for $2,133.00 and a maintenance letter for Cedar Lake Storage as presented; motions carried unanimously.

The council then approved two Shades Phase 2 contractor pay requests: pay request #3 for $268,468.26 and pay request #4 for $226,965.02, each supported by recommendation letters from consulting engineer Christopher B. Burke; both motions passed by roll call 6–0. Council discussion noted a narrow Community Crossings grant submission window and the potential to apply for up to $1,000,000 in grant funding if project paperwork is submitted on time.