Council approves update to Sewer Master Plan, city to survey ~130 new manholes

Vernal City Council · January 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Vernal City approved moving forward with a two-part update to the 2009 Sewer Master Plan: surveying approximately 130 new manholes within city limits and updated hydraulic modeling; estimated Vernal cost about $40,000 with a possible CIB planning grant of up to $50,000.

Public Works Director Keith Despain explained that the original 2009 Sewer Master Plan—prepared through a regional effort—requires updating due to growth and system expansions. The proposed two-part update would fund surveying of roughly 130 new manholes within Vernal and updated hydraulic modeling and planning estimated at about $130,000 for the regional work.

Staff will apply to the Community Impact Board for a planning grant of up to $50,000; Vernal City's direct cost was estimated at approximately $40,000 based on a per-manhole surveying fee. Councilmembers noted the update was overdue and necessary for capacity planning; the Council approved moving forward with the update and noted the Sewer Management Board would manage contracting and data compilation.