New EMS station 60% complete; project under budget and supported by grants

Grand County Board of County Commissioners · April 7, 2026

Summary

County project manager reported the EMS station is about 60% complete, under budget, and roughly a month ahead of schedule with solar installed and most interior work under way; grant reimbursements total more than $1.2 million to date and additional funds are pending.

Project Manager Jeff Hickam told the board the new EMS station is approximately 60% complete, with exterior and interior framing finished, insulation in place, solar panels installed and drywall nearly finished in the administrative areas. "We are approximately 60% complete with the building now," Hickam said (Jeff Hickam, Speaker 5).

The project remains under budget and is tracking a month ahead of schedule; current estimates place final completion between September and November 2026. Hickam summarized the grant funding status: DOLA reimbursements and a Connected Care grant have delivered more than $1.2 million to date and Freeport-McMoRan funding will cover furniture, fixtures and equipment.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source