Willard council weighs sewer requirement for Mountain Bay subdivision as developer warns of large costs
Summary
At a special Aug. 28 work session, Willard City Council and staff discussed annexation conditions for the Mountain Bay subdivision; the Planning Commission recommended installing a dry sewer line before road construction, while developer representatives said doing both sewer and septic is financially unreasonable. The council agreed to coordinate with Willard Partners LLC on timing.
Get email alerts on the Sewer Infrastructure topic
No spam. Unsubscribe anytime.
Willard City leaders met in a special work session Aug. 28 to discuss the annexation and infrastructure conditions for the Mountain Bay subdivision. The Planning Commission recommended that a dry sewer line be installed before the developer constructs the road to limit future costs to the city and to future residents.
Developer representatives, described in the record as Mr. Judd and Mr. Poll, told the council that installing both a sewer line and septic systems would be a significant financial burden. The transcript records that "the developer explained that putting in sewer and septic tanks is financially unreasonable and they can’t afford to do both." Council members pressed on how the timing of a sewer extension could affect fiscal responsibilities.
City staff noted that "the state’s new law requires that any unincorporated property apply for annexation to the nearest municipality before any land use application is made," and that Willard City accepted the annexation with the understanding sewer service would be provided to the subdivision. Mayor Travis Mote framed the council’s obligation in fiscal terms, saying, "it is the council’s responsibility to protect the future welfare of the city, including minimizing costs."
Council and developer representatives agreed to follow up: Mr. Judd and Mr. Poll said they would work with Willard Partners LLC to determine the current status of the sewer line project and when an extension might be completed. No formal motion or vote was recorded at the work session.