Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Utility Relocation topic

No spam. Unsubscribe anytime.

County to consider partial payment after Raglan water relocation bids rise

St. Clair County Commission · January 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Raglan Water requested a partial payment of $63,893.09 after the relocation contract rose to roughly $204,773 from an earlier $149k estimate; commissioners agreed to take action at Tuesday's meeting with reservations.

Dan reported that the Raglan Water line relocation—needed to build a bridge—has a revised contract figure higher than the initial estimate. Staff said the contractor requested a partial payment of $63,893.09 to keep work moving while weather slowed progress, and commissioners voiced concern about a roughly $54,000 increase compared with earlier projections.

Commissioners agreed the item should appear on the Tuesday agenda for formal action, with staff noting the county had previously agreed to reimburse relocation costs and that the low bidder remained the contractor on the project. No final payment or amendment was approved at the work session; the commission asked for documentation of bids and the revised contract pricing before voting.