Supervisors approve Change Order No. 2 for DD4 Lot 11 (Mallard WPA) after contractor encounters sandier soils
Summary
The board approved Change Order No. 2 for DD4 Lot 11 (Mallard WPA) to address sandier-than-expected soils; staff said the additional bedding sand should allow contractors to progress and may be offset by material savings elsewhere on the project.
Get email alerts on the Infrastructure Construction topic
No spam. Unsubscribe anytime.
Kossuth County supervisors approved Change Order No. 2 for DD4 Lot 11 (Mallard WPA) to provide additional bedding material after contractors encountered sandier soils at the work site.
A staff member explained the contractors "encountered some, sandier soil," which increased bedding requirements; he added that some offsets in other materials may reduce the net impact. Supervisor Decker moved to approve the change order and Supervisor Grama seconded the motion. After brief discussion, the board approved the change order by voice vote.
Staff said the additional bedding should allow the project to continue and that they do not expect another change order unless conditions worsen. Project contractors are progressing but working more slowly where individual lateral connections require more effort.