Council approves Community Center renovation GMP and funding plan totaling up to $7.02 million
Summary
Council approved a guaranteed maximum price (GMP) of $6,508,547 and authorized total project funding not to exceed $7,020,380 for a full-scope renovation of the Wickenburg Community Center, including structural fixes, ADA upgrades, and expanded kitchen and event spaces.
Get email alerts on the Community Center topic
No spam. Unsubscribe anytime.
Project Manager Todd Wallace told the Council that the Community Center sits on a roughly 4-acre property and has about 10,000 square feet of indoor space. The full-scope design includes structural repairs, roofing and truss work, new HVAC/electrical/plumbing systems, ADA-compliant restrooms and access, a new fire alarm and sprinkler system, enclosure of the patio (adding 2,153 sq ft), a 1,009 sq ft banquet room created by a movable partition, and a 70 sq ft kitchen expansion.
Caliente Construction produced a Guaranteed Maximum Price (GMP) of $6,508,547 after soliciting subcontractor estimates; staff identified variances from a prior 60% estimate and proposed funding by delaying FY27 CIP projects totaling $1.35 million, transferring $670,380 from general fund contingency, and using the existing $5 million CIP allocation for a total available funding package of $7,020,380. The Council approved execution of the Caliente cooperative purchasing contract, authorized up to $511,833 for additional related costs, and approved total project costs not to exceed $7,020,380. Vote: 7–0.