Commissioners approve final change order, authorize chairman to sign McPherson County building completion certificate

McPherson County Board of Commissioners · August 3, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Fuqua Construction presented change order No. 4 and a certificate of substantial completion for the McPherson County building; commissioners approved a net contract decrease and authorized the chairman to sign the certificate and a dedication-plaque purchase was later approved.

Fuqua Construction presented the final change order for the McPherson County Building Project and a certificate of substantial completion, and the Board of County Commissioners approved the change order and authorized the chairman to sign the completion certificate.

At the meeting, a Fuqua Construction representative (listed in the transcript as speaker 9) walked commissioners through 16 line items that together produced a net contract decrease of $33,537.04 and asked the board to sign a certificate of substantial completion. The representative said, "It's our final change order for the McPherson County Building Project." He also summarized schedule and warranty details: the contract date was recorded as 10/21/2024, the reported finish date was 06/04/2026, and the warranty would begin 06/05/2026 for one year.

Commissioner (speaker 6) moved to approve change order No. 4 and to authorize the chairman to sign the completion certificate; Commissioner (speaker 2) seconded the motion. Chair (speaker 1) called for the vote and the motion carried.

The Fuqua representative listed notable line items included in the change order: builder's risk insurance added $22,323 (balance due $6,568), a $11,270 deduct for reusing existing hollow metal doors and frames, a $9,136.35 deduct for salvaged demo materials, minor adds such as $2,600 for furniture installation oversight, $1,206.65 for dumpster/dump fees, $5,765 for added cameras and data, and other allowances adjustments that together produced the net decrease noted to commissioners.

After approving the change order and certificate, commissioners discussed a proposed 16-by-20 dedication plaque at an estimated cost of about $2,000 for display on the first floor. Commissioner (speaker 2) moved to approve the purchase of the McPherson County building sign (estimated $2,000); the motion carried. The Fuqua representative said the company would assist if the county wanted and noted donation(s) might help reduce the net outlay.

What happens next: the chairman is authorized to sign the certificate of substantial completion; the contract and warranty start dates were announced in the meeting and staff will process plaque procurement and any donor contributions.