Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Ga Apron Rehab topic
No spam. Unsubscribe anytime.
Board approves $246,532 change order and 20‑day extension for GA apron rehab
Summary
The board approved Change Order No. 1 for the 2026 GA Apron Rehab, not to exceed $246,532, and approved Amendment A adding 20 construction days for a cost not to exceed $30,000. Both motions passed at the May 19 meeting.
Get email alerts on the Ga Apron Rehab topic
No spam. Unsubscribe anytime.
During the engineer's presentation the board considered contract changes tied to the GA Apron Rehab project.
Mr. Fielder moved to approve the GA Apron Rehab Change Order No. 1 between the Airport Board and Powder River Construction for an increase in costs associated with the required PCI increase, "with the amount not to exceed Two Hundred Forty-Six Thousand, Five Hundred and Thirty-Two Dollars and No/100 ($246,532.00)," seconded by Mr. Bennett; the motion carried. In a separate motion Mr. Bennett moved, and Mr. Fielder seconded, to approve Task Order No. 8 Amendment A to add 20 additional construction days for Powder River Construction for a cost not to exceed $30,000; that motion also carried.
The board approved both the additional funds and the schedule extension to accommodate project needs; staff and the engineer will continue to coordinate with the contractor for sequencing and final accounting.
