Engineer notifies commission of Dec. 19 completion deadline for Trapper Road bridge project

Vernon County Commission · December 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Zach Olivas of Great River Engineering notified the Commission about a December 19, 2025 deadline for completing BRO-R108(45), the Trapper Road Bridge, flagging a schedule milestone for the project.

The Commission received a notice from Zach Olivas with Great River Engineering regarding the December 19, 2025 deadline for BRO-R108(45), the Trapper Road Bridge, to be completed. The entry highlights an important contract or grant-related completion date for the project.

The minutes do not state whether the deadline was met or the consequences of noncompliance; the notice was entered for the record and flagged as a schedule item requiring awareness by the Commission and staff.