Board awards CMAR contract for 117 E. Solomon Street reconstruction, seeks historic facade approval
Summary
Spalding County recommended awarding the CMAR contract for reconstruction at 117 East Solomon Street to Headley Construction and required that design features — including historically appropriate facade and window choices — return to the board for approval before construction.
Get email alerts on the Solomon St Reconstruction topic
No spam. Unsubscribe anytime.
The board voted to approve a recommendation to award the construction management at‑risk (CMAR) contract for reconstruction at 117 East Solomon Street to Headley Construction, with a requirement that final design details be returned to the board for approval.
Commissioners and staff emphasized the importance of historic accuracy for the downtown facade and asked that materials and window details be included in design submissions. A commissioner said the county will bring design features back to the board for approval and staff confirmed the CMAR award covers preconstruction and management functions; the actual construction contract will come later after the board reviews the proposed design.
The board approved the recommendation and staff confirmed they will present the final facade design for commissioner approval before construction begins.