Caldwell Tank submitted a payment application for $53,516.29 and Benton & Associates requested $3,160.75; the board heard the requests and was told tank erection is scheduled to begin April 23.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
At the April 3 meeting Troy Rhoads presented a payment application from Caldwell Tank for $53,516.29 and a requested payment to Benton & Associates of $3,160.75. The record shows the contractor scheduled erection of the tank to begin April 23.
The minutes record the amounts as payment requests presented to the board; they do not indicate an explicit board vote to approve those specific invoices at the meeting. The board discussed the schedule for tank erection and related procurement as part of the broader water infrastructure agenda.