Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Caldwell Tanks topic
No spam. Unsubscribe anytime.
Caldwell tanks project 80% complete; engineering amendment expected as budget nears exhaustion
Summary
Benton & Associates told the Board the Caldwell tanks project is about 80% complete and expected to finish within the next 30 days; an engineering amendment will be submitted because the project budget is nearly expended after being bid twice and about $46,000 of contingency remains.
Get email alerts on the Caldwell Tanks topic
No spam. Unsubscribe anytime.
Benton & Associates reported the Caldwell tanks project is currently about 80% complete and is expected to be finished within the next 30 days. The consultant said the project budget is nearly expended — in part because the project had to be bid twice — and will require an engineering amendment to continue work.
Minutes note there is about $46,000 in contingency remaining for the tank project. Benton & Associates will submit an engineering amendment as that budget is nearly expended; the Board discussed the project timeline and contingency but recorded no additional motions specific to the amendment at this meeting.
