Consultant reports elevated tank project delay; 30-day in-service requirement noted
Summary
Benton & Associates told the board piping work for the elevated tank is underway but the tank must be in service for 30 days before use; the consultant said the project will likely be 30–45 days past the substantial completion timeline and suggested contingency funds could replace nearby valves.
Get email alerts on the Water Tank Project topic
No spam. Unsubscribe anytime.
Troy Rhoades reported that piping work is underway for the village’s Elevated Tank Project and noted the technical requirement that "The tank must be in service for 30 days before being in use." He told trustees he did not believe the project would meet the scheduled substantial completion date and that it "will likely go 30-45 days passed." Rhoades added that any remaining contingency might be used to replace nearby valves.
The board received the update as an informational report; no contract change or formal schedule revision was recorded in the minutes. The consultant’s timeline indicates potential costs and scheduling impacts that village staff will need to address in subsequent meetings.