Montgomery advances wastewater project toward bidding; Hoyle Tanner proposal pending

Selectboard & Water Commission · February 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff reported plans to release the existing wastewater plan set to bid by March 1, open bids in mid-April with a 60-day bid-validity window, and address final-design issues by June while preparing a draft ID permit for public comment.

Montgomery public works staff told the Selectboard the municipal wastewater project is moving toward a public bidding phase. The town intends to put the existing plan set out to bid by March 1, open bids in mid-April and rely on a 60-day bid-validity period to reach a June milestone for resolving outstanding final-design issues.

The board was also informed that a proposal from engineering firm Hoyle Tanner for continued services is pending and that staff are working with WID to issue a draft ID permit for public comment. No formal vote on the contract was taken at the Feb. 16 meeting; the board received the update and will consider contracting steps as the permitting and bidding schedule advances.