Council approves $504,815.25 change order for Phase II water and wastewater project
Summary
The Redfield City Council approved Change Order #3 for the Water & Wastewater System Improvements Project, Phase II, adding $504,815.25 in costs and milestone dates pending USDA Rural Development concurrence; the approval was unanimous on a roll call vote.
Get email alerts on the Water Wastewater topic
No spam. Unsubscribe anytime.
The Redfield City Council approved Change Order #3 for H & W Contracting, LLC on the Water & Wastewater System Improvements Project, Phase II. The council voted to add milestone dates and accept the additional cost of $504,815.25 pending concurrence from USDA Rural Development; the motion passed on a roll call vote with all members voting “Yes.”
Engineer/representative Leif Redinger discussed the change order and construction milestone dates with the council before the vote. The approval was recorded as a formal council motion (Motion by Matthew Weller, seconded by Amy Akin). Council minutes do not record further specification of the line-item allocations or an immediate funding source in the motion text.