Board weighs phased approach to RFP and 90% design to control cost

Los Olivos Human Services District Board · July 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff extended the RFP response date to Aug. 1 and reviewed options for taking design work to 90% vs. phasing at 60% to save time and money; staff estimated full 90% for both options could cost about $375,000 and that a phase at 60% could reduce that by roughly $75,000.

District staff told the board the RFP for 90% design work was posted with an initial July 18 deadline but was extended to August 1 to increase vendor participation. The RFP includes a question-and-answer process so all vendors receive consistent information and staff expects four or five responses.

Board members debated whether to require full 90% design for both treatment options or to budget a phased approach: take both options to 60% and then let the board decide whether to carry one or both to 90%. Staff said some vendors already plan to structure proposals to allow that flexibility. General Manager Savage estimated that taking both options to 90% could cost roughly $375,000 and that stopping at 60% for one option could lower the cost by about $75,000.

The board signaled consensus for a phased approach with a 60% check-in point and gave staff direction to add clarity to the RFP Q&A so vendors can respond with flexible work packages. Staff will have a technical-subcommittee review of proposals and then bring recommendations to the full board.