Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Change Order topic

No spam. Unsubscribe anytime.

Building committee issues CCD #1 for structural-steel revisions at Horace Porter School

Horace W. Porter HVAC Building Committee · July 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Horace W. Porter HVAC Building Committee approved issuance of CCD #1 to address structural-steel revisions tied to PCO #22, noting a corrected PCO value of $96,318.60 and that the contractor declined to revise its proposal.

The Horace W. Porter HVAC Building Committee voted July 20 to issue a change‑control directive (CCD #1) to Sav Mor Plb & Heating Inc. to address structural‑steel revisions associated with PCO #22. JRR and SPA structural engineer reviewed adds and credits; Bob Banning and JRR recommended the CCD because delaying the work beyond the summer break would materially affect the project schedule.

JRR noted the PCO log (dated 7/10/26) and a corrected PCO #22 value of $96,318.60. The minutes state that "Motion by Dave Geissert, Seconded by Guy to issued CCD #1 to Sav Mor Plb & Heating Inc. Motion Carried 3-0-0." The record also states that Sav Mor declined to revise its proposal, which prompted the committee to authorize CCD #1 to proceed with the work this summer.