Building committee issues CCD #1 for structural-steel revisions at Horace Porter School
Summary
The Horace W. Porter HVAC Building Committee approved issuance of CCD #1 to address structural-steel revisions tied to PCO #22, noting a corrected PCO value of $96,318.60 and that the contractor declined to revise its proposal.
Get email alerts on the Change Order topic
No spam. Unsubscribe anytime.
The Horace W. Porter HVAC Building Committee voted July 20 to issue a change‑control directive (CCD #1) to Sav Mor Plb & Heating Inc. to address structural‑steel revisions associated with PCO #22. JRR and SPA structural engineer reviewed adds and credits; Bob Banning and JRR recommended the CCD because delaying the work beyond the summer break would materially affect the project schedule.
JRR noted the PCO log (dated 7/10/26) and a corrected PCO #22 value of $96,318.60. The minutes state that "Motion by Dave Geissert, Seconded by Guy to issued CCD #1 to Sav Mor Plb & Heating Inc. Motion Carried 3-0-0." The record also states that Sav Mor declined to revise its proposal, which prompted the committee to authorize CCD #1 to proceed with the work this summer.