Council grants conditional approval to add ~96 EDUs after Well 4R testing; chemical storage building timeline set
Summary
The council granted conditional approval to recognize about 96 additional EDUs from Well 4R pending receipt of a Certificate of Potability and written confirmation from engineer GMB; GMB has also requested a Rauch commitment that a chemical storage building be completed by March 1.
Get email alerts on the Water Capacity Well 4R topic
No spam. Unsubscribe anytime.
James Cook updated the council on Well 4R, reporting the well "is producing better than expected and based on the production numbers provides the Town will approximately 96 additional EDUs." He said GMB engineer Katherine McAllister confirmed the numbers and submitted her recommendation letter. The council voted to grant conditional approval to add the 96 EDUs, effective upon issuance of a Certificate of Potability for Well 4R and written confirmation from GMB that the well is operational and integrated into the water treatment plant.
Cook also told the council the chemical storage building tied to the project has an 8–12 week lead time and is expected to be completed in January or February; Katherine requested a letter from Rauch stating the chemical storage building will be done by March 1. The council recorded the condition and approved the conditional capacity recognition unanimously.