Board extends final site plan for 846 Ridge Street for one year

Peekskill Planning Board · February 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Planning Board approved a one-year extension for final site plan approval at 846 Ridge Street after staff said Con Edison coordination delayed required utility work; extension now expires in January 2026.

The Peekskill Planning Board granted a one-year extension for final site plan approval at 846 Ridge Street, citing ongoing utility coordination with Con Edison.

Planning staff reported the delay is driven by Con Edison responses regarding surface lines; the board approved the extension to expire 01/24/2026. The motion passed by voice vote with no roll-call recorded in the transcript.

Board members asked staff to continue monitoring the utility coordination and to confirm the expiration date with the applicant before the next review.