Commissioners approve $7,661 change order and $789,468.16 draw for 425th Ave. paving

Kingsbury County Board of County Commissioners · June 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved Change Order No. 1, adding $7,661.43 for a culvert modification and beaver-dam removal on the 425th Ave. paving project, and authorized Draw Request No. 3 totaling $789,468.16 to pay contractors and designers.

The Kingsbury County Board of County Commissioners approved Change Order No. 1 for the 425th Avenue paving project and authorized a draw to cover contractor and consultant invoices. Andrew Kangas of Civil Design told the board the change order covers an 18-inch culvert modification and removal of a beaver dam, adding $7,661.43 to the project cost.

Auditor Echo Steffensen presented Draw Request No. 3 totaling $789,468.16, which the agenda item breaks down as $757,057.34 for asphalt paving, $29,540.00 for civil design and $2,870.82 for Kingsbury Electric. The board approved the draw request and authorized Chairman Kyle Lee to sign the paperwork at the June 4 meeting.