Contractor outlines remaining bond packages; district still under budget
Summary
A Gallagher Construction representative presented remaining bond packages (concrete, technology, excavation), explained added change‑order estimates and materials testing costs, and reported the bid sheets indicate the project remains about $18,529 under budget.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Nathan from Gallagher Construction presented the remaining bond packages to the board and outlined which packages were highlighted for approval at the meeting: a concrete package (03B), technology packages (27A, 27B, 28B) and an excavation package (31A). He described added items and change‑order estimates tied to new drawings and vendor notifications and said engineers and materials‑testing costs had been added to the scope.
Nathan closed the presentation by reporting, "all in all, continuing to that last page, we're $18,529 under budget still." He left the floor for questions; the transcript records the presentation and the budget status but does not record a formal board vote on the remaining packages within the provided segments.