Commission weighs sidewalk termination, escrow and bus-stop safety for Peck Road subdivision
Summary
Engineers and commissioners debated whether to require a sidewalk connection to Peck Road or accept an escrow/fee; engineer said the proposed sidewalk currently stops about "10, 15 feet" short of Deck/Peck Road due to a guide rail and culvert constraints.
Get email alerts on the Sidewalk Escrow topic
No spam. Unsubscribe anytime.
Commissioners pressed the applicant on where the new sidewalk would end and how schoolchildren and other pedestrians would reach Peck Road. Chris Daley of Howell Engineering said the sidewalk "terminated the sidewalk probably, I'd say, about 10, 15 feet away from Deck Road," and explained the location was chosen because a guide rail and a reconstructed culvert limit where a sidewalk can safely connect across Peck Road.
Staff and applicants discussed alternatives including placing money in escrow or using a fee in lieu so that when a crossing or sidewalk connection is later feasible the township could extend the path. One commissioner emphasized the need to ensure children have a safe place to wait for the bus and raised concern that a sidewalk that terminated too far from Peck Road could force pedestrians into the roadway.
Commissioners also noted the absence of sidewalks along much of Peck Road and said the township's active-transportation planning work could affect where future connections make sense. The commission did not force a sidewalk across Peck Road at this meeting but asked for cost estimates and clarified whether escrow or a fee-in-lieu would be appropriate.