Utility details reliability work, phase balancing and possible future substation

Planning and Land Use Commission, Town of Castle Valley · August 14, 2025

Summary

Rocky Mountain Power explained technical details of the proposed Castle Valley work: a feed that will allow phase balancing for roughly 370 meters, the conversion of 69kV down to 25kV at a substation, and scoping for a possible future substation that could improve reliability but remains several years out.

The utility representative provided technical context for the project, saying the system currently brings a 69,000-volt transmission feed into the area, steps it down to 25,000 volts at a substation and distributes power radially across the valley. The company described a plan to add an additional 3-phase feed within town so loads can be balanced across phases and a single outage would affect a smaller share of customers.

"I take 69,000 volts from a transmission line ... and I had [a] substation that I built last year ... and we've been putting a new substation where we convert that 69,000 volts down to 25,000 volts," the utility representative said while outlining the system topology. The representative said that a potential additional substation on nearby BLM property is being scoped but remains several years away, dependent on permits, funding and engineering.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source