Resident urges council to halt Perry Street phase 2 after unsatisfactory phase 1 work
Summary
A resident told the council that phase 1 drainage work near Perry Street left trees removed and problems unresolved; neighbors oppose phase 2, which would run through an easement on private property, and asked the borough to clarify scope, funding and next steps.
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
Lisa Greenberg, who identified herself as a resident and said she has lived on the affected block for 15 years, urged the council to clarify whether the planned phase 2 drainage work would run through an easement on her property and remove trees that neighbors want left intact.
"We don't want part 2 because of what we saw, what happened with the part 1," Greenberg said, arguing that part 1 had produced poor results and that neighbors feared the same outcome for their properties. She said an easement on the south side of Fort Perry Street has formed a longstanding pond and that residents have endured mosquitoes and flooding for years.
Council members asked staff to bring Tom (the project manager) to the next meeting to explain the planned scope and to confirm the grant and budget status; staff said some grant funds were used for phase 1 and that final paving is tied to DOT grant schedules. The council agreed to ask for an explicit explanation of what 'phase 2' entails and for a meeting where neighbors, DPW and the project manager can review plans before further work proceeds.