Frank Middle School construction "on schedule and within budget," district says

Lenoir County Board of Education ยท August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District construction managers told the board the new Frank Middle School is on schedule with a planned early-2027 opening, reporting 378 days on site of 568 planned, zero lost-time incidents and 281 quality observations so far.

Speaker 2 told the Lenoir County Board of Education that the Frank Middle School project is advancing and that the district expects to deliver the building in early 2027. "This project continues to move forward on schedule and within budget with the finish line in sight for early 20 27," the presenter said, noting the site has been occupied 378 days of a planned 568-day schedule and that the team has recorded 281 quality observations to date.

The update listed recent work completed and upcoming milestones: glass installation in areas 300, 400, 500 and 600; finished brickwork in Area 200; fire pump set and downspouts tied into storm drains; and installation of water-source heat pumps in classroom wings with temporary cooling in place during work. Speaker 2 said safety remains a priority and reported "0 lost time due to safety incidents," and described August work to finish sprinkler rough-ins, ceilings and tile and to begin framing storefronts and exterior finishes. Board members asked clarifying questions about schedule and quality controls; the presenter said tours for teachers, staff and maintenance are already taking place to help visualize the completed facility.