Mannsville reports heavy water-plant use, filter changes after interconnect closure
Summary
Village water operator said closure of an interconnect increased plant run time from an average 1.5 hours to nearly 9 hours per day; Ellisburg used roughly 2.6 million gallons and was billed about $8,800, and staff replaced 10 filters and noted pumphouse leaks.
Get email alerts on the Water Operations topic
No spam. Unsubscribe anytime.
The village's water operator, Norm Jones, told trustees at the Oct. 1 meeting that closing a water interconnect has significantly increased plant operations and maintenance needs.
Jones said Ellisburg used about 2.6 million gallons and was billed more than $8,800 during the recent period. He said the plant, which normally runs about 1.5 hours per day, operated nearly nine hours daily while the interconnect was open; staff changed 10 filters after the line was closed and observed additional leaks and wear in the pumphouse. Ron Elmer of P&T is sourcing parts to repair a leak in the analyzer; Jones said repairing the analyzer will require briefly shutting down the pump.
The board discussed whether to seek bids for a replacement tractor and noted the need for pumphouse repairs and parts to restore normal operations. No timeline or cost estimates for the pumphouse repairs were recorded in the minutes.