Court authorizes up to $17,000 for pavilion steel soffit panels
Summary
Jeff Heffelfinger presented a construction report and the Commissioners' Court approved up to $17,000 for steel soffit panels at the pavilion; the motion carried without opposition on Feb. 9.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Construction representative Jeff Heffelfinger presented a construction report on the Extension Building/pavilion. Commissioner Nicholas Thomas moved to approve up to $17,000 for steel soffit panels to be installed at the pavilion; Commissioner Tim Alexander seconded the motion, which carried unopposed.
The motion authorized expenditures "up to $17,000.00" for steel soffit panels; the minutes do not specify the vendor contract particulars or the account from which the funds will be drawn. The court also received a separate presentation on museum repairs from Heffelfinger during the meeting.