Bond 2022 construction: Rockport-Fulton High at 21% complete, Fulton Elementary at 60%

Rockport-Fulton Independent School District Board of Trustees · October 17, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Teal Construction and Claycomb Associates reported progress on Bond 2022 projects: Rockport‑Fulton High School work is 21% complete and Fulton Elementary work is 60% complete; presenters answered trustee questions about the monthly schedule and status.

Teal Construction and Claycomb Associates gave the board a monthly update on Bond 2022 construction projects. Jamin Welch and Josh Hansen told trustees that work on the Rockport‑Fulton High School campus is 21% complete while the Fulton Elementary campus is 60% complete. The firms filed the monthly progress report and took questions from the board.

The presentation focused on construction progress and schedule milestones; the minutes do not record additional dollar figures, specific schedule dates, or change orders. Board members asked questions and received answers from the project representatives. The report was informational and no formal action was taken during the presentation.