Board warned of leaking boiler; short-term repairs planned and larger replacement possible
Summary
Facilities staff reported boiler No. 1 has been shut down after developing leaks; short-term welding and resealing are planned while staff evaluate whether full replacement is necessary given long lead times for steel parts.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Facilities staff told the board that boiler No. 1 began leaking and has been taken offline. Short-term plans include welding, filing and installing a gasket kit to seal the leaking sections and maintain heat through the winter. The presenter said the longer-term option may require replacing multiple sections, which could be time-consuming because of current supply constraints.
As context, the presenter said parts for the previous boiler refurbishment cost about $1,900 per section; the current boiler is larger and staff said final cost estimates are not yet available. The administration said it would bring any large-dollar replacement request back to the board for approval and reminded trustees that the district’s reserved metal-mines funds are intended for emergency capital work.