Kenilworth receives construction update on Lakefront Improvement Project

Village of Kenilworth Board of Trustees · January 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Bulley & Andrews presented a progress update on the Village’s Lakefront Improvement Project, including added access‑ramp costs, pending change orders, contingency use, weather-related lost days and a drone-assisted site video; trustees asked about the critical completion path and unforeseen construction challenges.

Representatives from Bulley & Andrews LLC updated the Board on the Lakefront Improvement Project during the Village President’s report. Project manager Michael Cottick reviewed safety, the project’s financial standing after adding an access ramp, pending change orders tied to unforeseen construction challenges and use of contingency funds. He presented photos of demolition and excavation and a drone video of the site.

Trustees asked for detail on likely unforeseen challenges, infrastructure installations and weather‑related delays and pressed about impacts to the project’s critical completion path. Cottick and his colleague Paul Attizoni addressed those concerns and described materials procurement and submittal status. President Cecily Kaz closed the presentation and thanked the Bulley & Andrews representatives.