Superintendent's report: construction, Bond 2023 timeline and enrollment at 10,069
Summary
NorthStar provided construction updates for multiple campuses and CFO Byron Bryant gave a Bond 2023 status and construction completion timeline; the district reported enrollment of 10,069 students and noted legislative engagement in Austin with Rep. Katrina Pierson.
Get email alerts on the Construction And Bond topic
No spam. Unsubscribe anytime.
During the superintendent's report, NorthStar representative Niels Berzanskis updated trustees on construction work at Moss Elementary, Magness Middle School, Worthy Fate High School and Royse City High School practice fields. CFO Byron Bryant presented a Bond 2023 update including a construction completion timeline.
Bryant also reported on recent legislative engagement: he participated in Rockwall County Days at the Capitol and met with Representative Katrina Pierson along with Board President Scott Muckensturm. Trustees thanked Bryant for representing district interests in Austin and emphasized the importance of state funding for schools; Muckensturm said the district's message was that "we want our kids funded, don't hold it hostage anymore."