Council authorizes replacement of wastewater plant circuit breaker after review of repair options
Summary
Council authorized replacement of the wastewater treatment plant's main circuit breaker after hearing estimates of $2,000 to repair or $5,000 to replace with a three-year warranty. Mayor Myers said replacement could proceed without agenda addition.
Get email alerts on the Utilities.wastewater topic
No spam. Unsubscribe anytime.
During the committee reports on Aug. 4, 2025, Alderman Gruner reported that the Wastewater Treatment Plant main circuit breaker could be repaired for $2,000 or replaced for $5,000 with a three-year warranty. Mayor Myers said the replacement could be authorized without adding the item to a future agenda and the new circuit breaker unit was authorized.
The minutes did not record a formal roll-call vote for this authorization; the entry reads that the unit "was authorized." The council did not provide further funding source details during the meeting record.