Council hears engineer: ADA ramps expected end of May, paving by end of June
Summary
Engineer reported the 2026 Street Project is underway, with ADA ramps expected to be finished by the end of May and paving completion targeted by the end of June; state permits for a Franklin St/Country Club stormwater project were also received.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The borough's engineering report confirmed the 2026 Street Project is active and provided a near-term timeline. "2026 Street Project is underway with the ADA ramps expected to be complete the end of May, paving completion by end of June," the minutes record; staff also said state permits for the Franklin St/Country Club storm water work were received and that work should start in July.
Jeff Shue, representing the engineer's office, recommended that the Charles Street bridge be discussed at a public works committee meeting so that inspection findings, scope of work, and bidding details — including any change-order work with York Excavating — are fully fleshed out before formal procurement steps.