Maybrook tables wastewater contractor payments; engineer reports leak and $170,000 CDBG award

Village of Maybrook Board of Trustees · January 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineer S. Hoffman told the Board two contractor payment applications for the wastewater/UV project were not received and were tabled; he also reported a likely outside-pipe leak found during UV testing and said the village secured a $170,000 CDBG grant to fund sewer work.

The Village of Maybrook tabled two contractor payment applications after Engineer S. Hoffman reported the applications were not received: General Contractor’s Application for Partial Payment No. 7 for the Wastewater Treatment Plant Effluent Disinfection project and General Contractor’s Application for Partial Payment No. 1 for the Sludge Digester Dumpster Roof. The Board left both items on the table until the paperwork is provided at a future meeting.

Hoffman also updated the Board on construction and testing: during clean-water testing of the UV system a leak was identified and engineers determined it was likely in outside piping where the system ties to a valve. Hoffman said the county has approved documents for a previously authorized CDBG project; he reported the village received a $170,000 Community Development Block Grant to support sewer work. The Clerk added that the UV grant was filed that day, and Trustee Capozzoli described upcoming contractor walk-throughs and a February schedule for the sludge-press roof work.