Florence awards $22,750 water-main improvements contract for White/Main and Seventh Day Road
Summary
The board approved Delta Constructors' low quote of $22,750.00 for water-main improvements at White Street & Main Street and Seventh Day Road. The motion passed unanimously at the Oct. 7 meeting following Public Works recommendation.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Street Director/Public Works David Myers recommended awarding the water-main improvement contract to Delta Constructors, Inc. The board approved Delta Constructors' low quote of $22,750.00 over Maintenance Systems, Inc.'s $24,900.00 bid.
Alderman Martin moved to accept the low bid and Alderman Sistrunk seconded; the motion carried unanimously. The minutes do not include a construction timetable or start date.