Florence approves pay request and authorizes Phase III sanitary sewer contract for Hwy 49 Eagle Post Road
Summary
The board approved Pay Request #7 to Hemphill Construction for $12,900.20 for Phase II sanitary sewer work and authorized Mayor Trey Gunn to sign a contract with Thornton Construction for Phase III pending attorney review.
Get email alerts on the Infrastructure Sewer topic
No spam. Unsubscribe anytime.
City Engineer Tim Parker presented pay requisitions and contract recommendations tied to the HWY 49 Eagle Post Road sanitary sewer additions. The board approved PAY REQUEST #7 to Hemphill Construction Company, Inc. in the amount of $12,900.20 for Phase II work; the vote record notes Alderman Mason Herrin did not participate on that item.
The board also authorized and directed Mayor Trey Gunn to execute the contract with Thornton Construction Company, Inc. for the HWY 49 Eagle Post Road Sanitary Sewer Additions Phase III project, contingent on city attorney review of the contract documents. That authorization carried with the same participation record noted for prior construction votes.