Water superintendent reports Rice Road break; flow meter at Bissel Pit replaced
Summary
At the April 30 meeting, Water Superintendent Keith Austin reported crews hit ledge and a retaining wall while repairing a Rice Road water break but expects four customers back online soon; an upgraded flow meter for Bissel Pit has been ordered after the previous unit failed.
Get email alerts on the Water System topic
No spam. Unsubscribe anytime.
Water Superintendent Keith Austin told the Town Board that a recent break on Rice Road encountered ledge and a retaining wall during excavation, complicating repairs but allowing crews to return service to four customers in the near term. The board was told the condition slowed progress but is being managed by highway and water crews.
Austin also reported that the flow meter at Bissel Pit failed and could not be repaired; the town has ordered an upgraded replacement for immediate installation. The board received Expenditure and Revenue reports in their packets and was updated about these operational matters during the Supervisor's report.