Public Works items advance: IEPA update on Well House 7, change orders approved, 100 meters purchased and two hires authorized
Summary
The committee received an IEPA update on the Well House 7 permit, approved two change orders for the Well House project totaling $12,177, authorized purchase of 100 final water meters for $49,100, and approved hires for Elijah Bowers and Brentyn Hammer.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Village engineer Adam Bunge told trustees that the Illinois Environmental Protection Agency verbally reported on Sept. 4, 2024 that the Well House 7 construction permit "should have been issued," though the village remains pending IEPA's official approval letter and must retest for radium and gross alpha during final well water quality testing for operating permits.
Trustees approved multiple Public Works items by voice vote. They authorized a purchase order to Core & Main for the final 100 water meters at a cost of $49,100 from line item 5382 (Water). They approved hiring Elijah Bowers as Maintenance Worker 1 at $21.00 per hour with a May 5, 2025 start date, and hired Brentyn Hammer as a part-time seasonal worker at $16.00 per hour for up to 600 hours starting June 9, 2025.
The committee also moved two DPI Construction change orders for Well House 7 to the Village Board: Change Order #29 for roof patching at $9,317 (line item 5400 2022 Water Project Fund) and Change Order #30 to install two rows of snow retention guards at $2,860. Both change orders were approved by voice vote. The engineering notes referenced ongoing punch-list work on the CV 2024 Streets Improvements Project and that Rock Roads has been awarded the CV 2025 Streets contract.