Engineers describe two Route 100 culvert replacements; detour could reach six miles

Londonderry Selectboard · July 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Gill Engineering presented plans to replace two undersized metal culverts north of Town Highway 49 with precast concrete boxes to improve hydraulics and stream connectivity; construction is anticipated in 2026 and could require single or separate closures with detours as long as six miles if both culverts close simultaneously.

A project manager with Gill Engineering briefed the Selectboard on proposed replacements of two culverts on Route 100 (identified in the presentation as Culvert 225 and Culvert 228), explaining the structures are hydraulically undersized and that the work would include roadway reconstruction and placement of precast concrete box culverts.

"The existing culvert is a 48 inch metal pipe culvert with 14 feet of cover," the project manager said, describing excavation, use of a crane and excavator, and staging that will require closing the roadway during installation. The presenter said construction is anticipated in the 2026 season with an end date of Nov. 15, and explained that if both culverts were closed at the same time "you're looking at a 6 mile, detour." He also said the team is coordinating with Green Mountain Power to relocate an adjacent utility pole ahead of construction.

Board members and the fire department representative discussed closure options and emergency access; the presenter said the preference is to use two separate, shorter closures where possible and to communicate scheduling and contractor responsibilities to reduce impacts on school buses and emergency vehicles. The project team committed to providing a look-ahead schedule and contractor contact information so the town can coordinate responses and notify affected residents.