Green Mountain Power outlines three-mile undergrounding on Londonderry circuit
Summary
Green Mountain Power told the Selectboard it plans a roughly three-mile mainline rebuild on a poor-performing circuit in Londonderry, placing about 95% of the new line underground and aiming to finish under the current construct by August.
Get email alerts on the Electric Infrastructure topic
No spam. Unsubscribe anytime.
Tim Jones of Green Mountain Power told the Londonderry Selectboard the utility has scheduled a targeted rebuild of one of the town's worst-performing circuits and expects to place most of the new main line underground.
"Londonderry is on 1 of those worst performing circuits," Jones said, describing a plan to place about "95% of this line" underground along a roughly three-mile stretch from Thompsonburg Road to the private-customer terminus. He said the work will include replacing culverts 24 inches or smaller "in kind," providing construction-notification letters to affected households and producing a look-ahead schedule the town can use to anticipate contractor activity. Jones told the board the project would move from installation to energizing and retire the old line over a period of months, with completion "by August at the latest" under the current construct.
Board members sought clarity about service connections and sequencing; Jones said the utility will cap buried services at homeowner locations to facilitate future individual tie-ins and that landowners who want immediate service upgrades will coordinate with GMP designers. The presentation emphasized outage reduction as the primary goal and included a commitment to provide the town with notifications and a contractor schedule so local officials and residents can plan for lane-control work and limited interruptions.