Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Council says Creek pump installation awaits AEP protection work
Summary
Merritt Engineering is completing a project plan for the Creek water project; the new pump cannot be installed until AEP places fiberglass protection over nearby lines outside the pump house.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Councilor Mike Mumper reported that Merritt Engineering is working on the project plan for the water project on Creek. The new pump's installation is contingent on American Electric Power (AEP) placing fiberglass protection over utility lines outside the pump house; the pump cannot be installed until that work is complete.
No timeline for AEP's work was provided in the meeting minutes. Councilors did not record any motion to change procurement or timelines; staff will follow up with Merritt Engineering and AEP to schedule the protection work and pump installation.
